Talakhovskaya CHPP

Location:

Kaliningrad region, Sovetsk

Technical characteristics:

  • Installed capacity: electrical - 160 MW;

  • Fuel in use: gas;

  • Equipment in use: #2 * GE PG 6111FA gas turbines;

Works performed:

  • Prime Contractor

  • Supply of the auxiliary equipment, materials;

  • Construction and erection work;

  • Installation of the main and auxiliary equipment;

  • Commissioning operations and preparations for the Plant start-up;

  • Performance of tests and involvement in the power generating equipment qualification;

  • Plant start-up.