News

01 August 2014

230 MW CCGT at Kirov CHPP-3 has been brought on line

A formal ceremony, dedicated to the 220MW CCGT startup at Kirov CHPP-3 (IES Holding) was held in Kirovo-Chepetsk. The CCGT construction was carried out by “Intertechelectro” Group of companies.

22 Jule 2014

Reliability run of the 230 MW CCGT at Kirov CHPP-3 has been successfully completed

Reliability run of the CCGT equipment has been successfully completed at Kirov CHPP-3 (IES Holding).

20 May 2013

Installation of the steam turbine generator at the 220 MW CCPP of Kirov CHP-3 has been completed

CJSC “Intertechelectro” carries on the construction of a 220 MW CCPP at Kirov CHP-3, incorporated in OJSC "TGC-5" ("IES-Holding").

27 August 2012

Construction of the gas turbine foundation for a 220 MW CCP at Kirov CHP-3 has been completed

CJSC "Intertechelectro" carries on the construction of a 220 MW CCP at Kirov CHP-3, which is part of OJSC "TGC-5" ("IES-Holding").