News

07 June 2011

Chelyabinsk HPP-3 3rd power unit is put in operation

The Chelyabinsk HPP-3 3rd power unit (OJSC Fortum) was formally put in operation on the 7th of June, 2011.

03 May 2011

Chelyabinsk HPP-3 rd power unit is tested successfully

CJSC Intertechelectro has successfully tested the Chelyabinsk HPP-3 225 MW CCGT 3rd power unit, OJSC Fortum being the customer.

20 September 2010

Major equipment is being installed at Chelyabinsk CHPP-3 power unit under construction

CJSC «Intertechelectro» is going on to build the 220 MW CCGT plant, Chelyabinsk CHPP-3 (branch of OJSC Fortum) power unit.

11 February 2010

GT unit and ST unit foundations are completed on the Chelyabinsk CHPP-3 power unit under construction

CJSC «Intertechelectro» is continuing to construct a 220 MW CCGT power unit, Chelyabinsk CHPP-3 (OJSC «Fortum») 3rd power unit.

21 August 2009

CJSC «Intertechelectro» has started to extend the 220 kV open switchgear of the Chelyabinsk CHPP-3 power unit under construction

CJSC «Intertechelectro» has started to extend the 220 kV open switchgear of the Chelyabinsk CHPP-3 (OJSC «Fortum») 3rd power unit under construction.

28 Jule 2009

CJSC «Intertechelectro» is completing structural steel installation of the Chelyabinsk CHPP-3 power unit under construction

CJSC «Intertechelectro» is completing installation works on the main building structural steel of the Chelyabinsk CHPP-3 (OJSC «Fortum») 3rd power unit– 220 MW CCGT power plant.

17 April 2009

Structural steel installation is being completed at Chelyabinsk CHPP-3

CJSC «Intertechelectro» is continuing works on construction of the Chelyabinsk CHPP-3 220 MW CCGT power unit #3 being the part of the OJSC «Territorial generating company №10» (TGK-10).

09 February 2009

Structural steel installation is commenced at the Chelyabinsk CHPP-3 3rd power unit

CJSC «Intertechelectro», general contractor of the Chelyabinsk CHPP-3 230 MW CCGT power unit construction, is getting prepared for the structural steel installation and is fulfilling the trusses site joint and columns erection

26 September 2008

CJSC «Intertechelectro» completes the foundations for the Chelyabinsk CHPP-3 3rd power unit frame

At the OJSC “TGK-10” Chelyabinsk CHPP-3 new CCGT power unit construction site the foundation works for the extended part of the main building are being completed. CJSC «Intertechelectro», the general contractor, is getting prepared to move the back wall.

05 May 2008

Intertechelectro CJSC begins the implementation of the combined cycle unit construction project at Chelyabinsk HPP-3

The engineering & construction company Intertechelectro (integrated in the Intertechelectro - New Generation Group of Companies) performs preparatory activities preceding the main stage of the combined cycle unit construction at Chelyabinsk HPP-3.

25 March 2008

Intertechelectro - New Generation Group of companies is expanding Chelyabinsk CHP-3

The Intertechelectro - New Generation Group of companies began the implementation of the Chelyabinsk CHP-3 expansion project.